Client happiness is at the forefront of Rapid Rail's ethos and we have certainly shown this over one of or busiest periods of the year.
Projects include:
Liberty Steel Stocksbridge -
Full re-rail: 2 x 243 meters of bridge rail to be removed in full including all existing fixings and replaced with A65 crane rail and new welded base clips throughout.
Work was conducted in the Liberty summer shutdown with crane rail joints puddle arc welded. Engineers worked on the open beam from Rapid Rail certified lifelines.
The project was successfully completed on time and with glowing audits.Arconic Birmingham -
Full re-rail both North and South rails of A2 Crane Cross Travel Rail, including the removal of the existing section by air arcing. Replaced with suitable billet stitch welded to an open beam whilst working from Scissor Lifts.
The project was successfully completed on time .